A DFM review is not a formality that delays the tool order. It is the last point at which a change costs hours instead of weeks, and the first point at which someone outside the design team looks at the part with the tool in mind.

Figure 1. Twelve-area DFM review checklist and review session workflow.
This checklist is organized the way a review actually runs: geometry first, then tooling, then process, then the commercial and quality questions. Use it as the agenda, not as a rubber stamp — a review where every box is ticked and nothing is questioned is a review that did not happen.
1. Wall thickness
- [ ] Nominal wall thickness defined and stated on the drawing
- [ ] Wall thickness consistent across the part
- [ ] Maximum-to-minimum wall ratio within 2.5:1
- [ ] Thick-to-thin transitions made gradually, over at least 3 × the difference
- [ ] No isolated thick sections that will sink or void
- [ ] Wall thickness appropriate to the resin (thin walls need high-flow grades)
- [ ] Flow length to thickness ratio calculated for the worst-case flow path
Ask: which wall is the thickest, and what does it do? Thick sections are usually there to carry load or to accommodate a feature, and both have better answers than more material.
2. Draft angle
- [ ] Draft specified on every vertical face, including inside faces and holes
- [ ] Draft in the direction of pull, not against it
- [ ] Extra draft on textured surfaces (1° minimum, plus 1° per 0.025 mm of texture depth)
- [ ] Deep features, ribs and bosses drafted generously
- [ ] Undercuts identified and either eliminated or assigned to a slide, lifter or stripping action
Ask: what is the texture, and does the draft account for it? Texture is the single most common cause of a part that will not release.
3. Radii and corners
- [ ] External corners radiused
- [ ] Internal corners radiused at ≥ 0.5 × wall thickness where possible
- [ ] No sharp internal corners at any stress location
- [ ] Fillet radius consistent with a standard cutter size the tool shop already owns
- [ ] Weld line locations evaluated against the stress pattern
Ask: does the radius at the corner match the wall thickness, or just look nice? A small fillet at a thick corner concentrates stress exactly where the part will fail.
4. Ribs
- [ ] Rib thickness 50–60% of the adjacent wall
- [ ] Rib height within 3 × wall thickness unless flow analysis supports more
- [ ] Rib spacing ≥ 2 × wall thickness
- [ ] Ribs drafted on both sides
- [ ] Root fillets specified
- [ ] Ribs staggered so they do not create a thick mass at the intersection
- [ ] Rib direction aligned with the principal bending load
- [ ] Sink on the opposite face checked at the rib locations
Ask: are the ribs carrying load, or just filling space? Ribs added without a load path simply add weight and sink marks.
5. Bosses
- [ ] Boss wall thickness ≤ 60% of the nominal wall (or ≤ 0.6 × the mating wall)
- [ ] Boss outside diameter appropriate to the fastener
- [ ] Boss connected to a wall or a rib rather than standing free
- [ ] Gussets added where the boss is tall or loaded
- [ ] Bosses drafted
- [ ] Core pins sized so the boss core can be cooled
- [ ] Boss base filleted into the wall
- [ ] Boss height within practical core-pin limits
Ask: which boss is the tallest and thinnest? That is the one that will snap in transport.
6. Holes, slots and threads
- [ ] Holes molded where practical (molded holes cost less than drilled holes)
- [ ] Core-pin length to diameter ratio within limits (typically ≤ 4:1 for a robust pin)
- [ ] Blind holes specified with a depth that suits the core pin
- [ ] Hole axis parallel to the mold opening direction
- [ ] Threads specified as molded, inserted or self-tapping and consistent with the joint load
- [ ] Thread relief and lead-in provided
- [ ] Side holes assigned to a slide or a secondary operation, with the cost understood
Ask: which feature needs the most fragile core, and does the design need it at all?
7. Gating and flow
- [ ] Gate type and location proposed
- [ ] Gate location approved by the customer if it leaves a visible mark
- [ ] Gate positioned so the melt fills thick sections first
- [ ] Gate positioned so weld lines fall in low-stress areas
- [ ] Gate size appropriate to the wall and the resin
- [ ] Runner system balanced for multi-cavity tools
- [ ] Cold runner versus hot runner decided, with a reason
- [ ] Degating method defined, and its cost estimated
- [ ] Flow analysis run for parts with long flow, tight tolerance or critical appearance
Ask: where does the flow end, and what is there? The last-filled point is where burns, short shots and weak welds live.
8. Cooling
- [ ] Cooling circuits laid out with adequate coverage
- [ ] Core cooling provided, not just cavity cooling
- [ ] Cooling distance from the surface consistent (typically 1.5–2.5 × the wall thickness)
- [ ] Baffles, bubblers or thermal pins specified for deep cores
- [ ] Cooling around thick sections given extra attention
- [ ] Circuit design matched to the warpage requirement
- [ ] Water fittings positioned so they do not clash with the machine or robot
Ask: which section of the part will be hottest at ejection? That is where the cycle time and the warp come from.
9. Ejection
- [ ] Ejector pin locations proposed
- [ ] Ejector pins land on rigid features, not on cosmetic surfaces
- [ ] Adequate ejection area for the part stiffness
- [ ] Ejector pins not interfering with cooling channels
- [ ] Stripper plate or air ejection considered for thin-wall or deep-draw parts
- [ ] Positive return and safety switches specified
- [ ] Part will not stick in the cavity by vacuum or by undercut
Ask: what is the ejection strategy, and does the part have enough stiffness to survive it?
10. Tolerances and dimensions
- [ ] Tolerances assigned only to functionally important dimensions
- [ ] General tolerance note stated on the drawing
- [ ] Tolerances achievable by molding, with machined or inserted features used only where needed
- [ ] Datum scheme defined for the checking fixture
- [ ] Warpage and flatness requirements realistic for the geometry
- [ ] Critical-to-quality dimensions identified and flagged for control
- [ ] Mating parts reviewed against the tolerance stack
Ask: which dimension, if it drifts, stops the assembly line? That one earns a tight tolerance; the others do not.
11. Material and process
- [ ] Resin grade specified with supplier and grade code
- [ ] Resin suitable for the wall thickness, flow length and environment
- [ ] Drying requirements documented
- [ ] Masterbatch carrier compatible with the base resin
- [ ] Regrind percentage allowed stated
- [ ] Shrinkage data available for the specific grade
- [ ] Additives, flame retardants or UV packages declared
- [ ] Cycle time and machine tonnage estimated
12. Quality, cost and program
- [ ] Appearance requirements defined (which surface is class A, which is hidden)
- [ ] Surface texture specified on the drawing, with the mold finish standard referenced
- [ ] Inspection plan and sampling frequency agreed
- [ ] Critical dimension list agreed with the supplier
- [ ] Quotation assumptions documented: cavitation, cycle time, tonnage, scrap rate
- [ ] Tooling ownership, maintenance responsibility and cycle-count expectation stated
- [ ] Change control process agreed for post-tool-release changes
- [ ] Timeline agreed with realistic time for tool trials and correction loops
Running the review
A DFM review works best as a live session with the part on screen, the tool designer present, and someone empowered to say no. Practical habits that make it effective:
- Review the drawing before the 3D model, then check the model against the drawing. Discrepancies are common and expensive.
- Walk the part in the direction of pull, feature by feature. Most moldability problems appear during this walk.
- Log every issue with an owner and a date, not just a note. Unassigned findings are decoration.
- Separate must-fix from nice-to-have. A DFM report that lists fifty equal-severity items gets ignored.
- Re-review after changes. A geometry change made late can invalidate the whole review.
The point of the checklist is not to produce a document. It is to move the discoveries that would otherwise appear at tryout — where they cost weeks — to the desk, where they cost an afternoon.